Downstream fish passage at the Revin power plant (08)

Project owner BAMEO

Type of project Construction of a downstream fish passage device

Replacement of the trash rack and creation of a downstream fish passage system comprising 5 outlets with a total flow rate of 1.35 m3/s.

Main technical features

DN1000 steel downstream fish passage pipe; trash rack with 20 mm spacing, inclined at 45°; trash rack support wall; energy dissipation basin (2.6 x 2.6 m).

Specific constraints

Works on existing facilities; upstream canal cofferdamming.

  • Location 08500 Revin
  • Project / construction cost 350 K €
  • Years of completion 2015 - 2016