Civil engineering rehabilitation of the Bergerac dam

Project owner EDF UP Centre - GEH DORDOGNE

Type of project Repair of civil engineering defects at the Bergerac dam in Dordogne

The works carried out were intended to strengthen the structures on the right bank of the Bergerac hydroelectric scheme: Treatment of watertightness defects in the debris-clearing canal by mortar and cement grout injections; Repointing of the upstream side wall, construction of an underwater containment wall, and mortar and cement grout injections; Repair of surface deterioration in the fish pass and pouring of a concrete slab.

Main technical features

The scheme consists of the submerged powerhouse on the right bank, a debris-clearing canal, a fish pass, a weir dam and an eel pass on the left bank. The powerhouse was built in 1968. Before that, the scheme served as a lock, when the Dordogne was still navigable (the embankment dates from 1850–1853). The fish pass dates from 1984, while the eel pass dates from 2010. The hydroelectric power plant is a run-of-river facility. It uses a maximum flow rate of 57 m³/s to operate its two fixed-blade bulb units, each rated at 725 kW.

Specific constraints

A reconnaissance dive was carried out to confirm the geometry of the deterioration, validate the selected techniques and establish the preliminary quantity estimates.

  • Location 24100 Bergerac
  • Project / construction cost 483,6 k €
  • Years of completion 2022