In 2019, HYDROSTADIUM signed a contract for the full project management of a small hydropower plant development project, including commissioning of the facility.
A semi-buried intake (PE) located at an altitude of 1,100 m, comprising a Tyrolean screen inclined at 30°, a U-shaped sand trap, a BMC and a head gate valve chamber (VDT); 2,300 m of fully buried penstock (CF) with a diameter of 400 mm; a hydropower plant equipped with a two-jet PELTON turbine; 1 MW power unit.
The specific feature is the integration of the facility into the landscape, with the PE and CF buried. The plant blends perfectly into its mountain environment.
Learn more...
Contact us
Access the details of a project by selecting a point on the map.