Demolition of the existing structures (fish pass and canoe pass) and earthworks. Construction of the new fish pass using sheet piles, as well as the new canoe pass with retarders.
The weir extends over a length of 287 m. On the left bank are the canoe pass and the fish pass, built in 1989 to replace a boat pass initially constructed together with the weir.
An exceptional flood of 1,000 m3/s on 14 July 2021 inundated the worksite and brought the works to a halt. Work resumed in spring 2022.